NJ Regulators Fine Data Center for Gas Generators ThatLack Permits
September 23, 2026 | njspotlightnews.org
State environmental regulators finer 25, 2026ed a South Jersey data center $1.07 million for allegedly operating dozens of pollution-emitting natural-gas generators without permits.
DataOne in Vineland was issued an administrative order and notice of penalty after a July 29 visit by Department of Environmental Protection inspectors on July 29. On site were 62 machines known as stationary reciprocating generators, or engines, that lacked permits, the department announced on Tuesday (9/24).
Read More: Click Here
NJ SEED: As important as data centers are to the emerging AI economy, it is equally important that they be held accountable for following the rules.